Client Building phases Periods Total building costs (mln euro)
Total Orders received by contractors 2023 1st quarter 4,936
Total Orders received by contractors 2023 April 1,873
Total Orders received by contractors 2023 May* 1,494
Total Orders received by contractors 2023 June* 1,899
Total Orders received by contractors 2023 2nd quarter* 5,266
Total Orders received by contractors 2023 July* 1,522
Total Orders received by contractors 2023 August* 1,295
Total Orders received by contractors 2023 September* 1,394
Total Orders received by contractors 2023 3rd quarter* 4,211
Total Orders received by contractors 2023 October* 2,044
Total Orders received by contractors 2023 November* 1,562
Total Orders received by contractors 2023 December* 1,674
Total Orders received by contractors 2023 4th quarter* 5,280
Total Orders received by contractors 2023* 19,694
Total Orders received by contractors 2024 January* 1,208
Total Orders received by contractors 2024 February* 1,888
Total Orders received by contractors 2024 March* 2,388
Total Orders received by contractors 2024 1st quarter* 5,484
Total Orders received by contractors 2024 April* 2,440
Public service and house-building corp. Orders received by contractors 2023 1st quarter 887
Public service and house-building corp. Orders received by contractors 2023 April 231
Public service and house-building corp. Orders received by contractors 2023 May* 264
Public service and house-building corp. Orders received by contractors 2023 June* 315
Public service and house-building corp. Orders received by contractors 2023 2nd quarter* 811
Public service and house-building corp. Orders received by contractors 2023 July* 271
Public service and house-building corp. Orders received by contractors 2023 August* 248
Public service and house-building corp. Orders received by contractors 2023 September* 154
Public service and house-building corp. Orders received by contractors 2023 3rd quarter* 673
Public service and house-building corp. Orders received by contractors 2023 October* 262
Public service and house-building corp. Orders received by contractors 2023 November* 243
Public service and house-building corp. Orders received by contractors 2023 December* 294
Public service and house-building corp. Orders received by contractors 2023 4th quarter* 800
Public service and house-building corp. Orders received by contractors 2023* 3,171
Public service and house-building corp. Orders received by contractors 2024 January* 236
Public service and house-building corp. Orders received by contractors 2024 February* 263
Public service and house-building corp. Orders received by contractors 2024 March* 285
Public service and house-building corp. Orders received by contractors 2024 1st quarter* 783
Public service and house-building corp. Orders received by contractors 2024 April* 409
Companies building for the market Orders received by contractors 2023 1st quarter 1,666
Companies building for the market Orders received by contractors 2023 April 1,003
Companies building for the market Orders received by contractors 2023 May* 519
Companies building for the market Orders received by contractors 2023 June* 937
Companies building for the market Orders received by contractors 2023 2nd quarter* 2,459
Companies building for the market Orders received by contractors 2023 July* 596
Companies building for the market Orders received by contractors 2023 August* 453
Companies building for the market Orders received by contractors 2023 September* 778
Companies building for the market Orders received by contractors 2023 3rd quarter* 1,827
Companies building for the market Orders received by contractors 2023 October* 1,240
Companies building for the market Orders received by contractors 2023 November* 661
Companies building for the market Orders received by contractors 2023 December* 624
Companies building for the market Orders received by contractors 2023 4th quarter* 2,525
Companies building for the market Orders received by contractors 2023* 8,476
Companies building for the market Orders received by contractors 2024 January* 464
Companies building for the market Orders received by contractors 2024 February* 1,001
Companies building for the market Orders received by contractors 2024 March* 1,208
Companies building for the market Orders received by contractors 2024 1st quarter* 2,673
Companies building for the market Orders received by contractors 2024 April* 1,005
Other private clients Orders received by contractors 2023 1st quarter 2,384
Other private clients Orders received by contractors 2023 April 639
Other private clients Orders received by contractors 2023 May* 711
Other private clients Orders received by contractors 2023 June* 647
Other private clients Orders received by contractors 2023 2nd quarter* 1,997
Other private clients Orders received by contractors 2023 July* 654
Other private clients Orders received by contractors 2023 August* 594
Other private clients Orders received by contractors 2023 September* 462
Other private clients Orders received by contractors 2023 3rd quarter* 1,711
Other private clients Orders received by contractors 2023 October* 541
Other private clients Orders received by contractors 2023 November* 657
Other private clients Orders received by contractors 2023 December* 757
Other private clients Orders received by contractors 2023 4th quarter* 1,955
Other private clients Orders received by contractors 2023* 8,047
Other private clients Orders received by contractors 2024 January* 509
Other private clients Orders received by contractors 2024 February* 624
Other private clients Orders received by contractors 2024 March* 895
Other private clients Orders received by contractors 2024 1st quarter* 2,029
Other private clients Orders received by contractors 2024 April* 1,027
Source: CBS.
Explanation of symbols

Table explanation


This table shows the value (expressed in building costs) of the construction of building projects expected shortly. It also shows the value of the actually realised monthly production of building projects. The figures relate to building projects with building costs of 50 thousand euro or more. The total building costs are broken down into alteration and new buildings and in building costs by building phase by type of client. The costs of new buildings are broken down by category of purpose.

Data available from: January 2015.

Status of the figures:
Figures on the latest 12 months are provisional.
Municipalities with non-response are estimated. The later received response of municipalities over previous periods have been processed in the figures of the month in which the building permit was granted. As a result, figures about the same month may vary over time. Twelve months after publication the provisional figures become definite.

Changes as of June 28, 2024:
The figures of April 2024 have been added and all figures as of April 2023 may be revised.

When will new figures be published?
The new figures will be published on the last working day of the second month after the reporting month. The figures for the same reporting month of a year earlier then become final.

Description topics

Total building costs
Sum of the building costs for alteration and new building of dwellings
and commercial and industrial building projects.