Client Building phases Periods Total building costs (mln euro)
Total Orders received by contractors 2020 January 1,228
Total Orders received by contractors 2020 February* 1,458
Total Orders received by contractors 2020 March* 1,638
Total Orders received by contractors 2020 1st quarter* 4,324
Total Orders received by contractors 2020 April* 1,781
Total Orders received by contractors 2020 May* 1,361
Total Orders received by contractors 2020 June* 1,559
Total Orders received by contractors 2020 2nd quarter* 4,701
Total Orders received by contractors 2020 July* 2,043
Total Orders received by contractors 2020 August* 1,147
Total Orders received by contractors 2020 September* 1,722
Total Orders received by contractors 2020 3rd quarter* 4,912
Total Orders received by contractors 2020 October* 1,956
Total Orders received by contractors 2020 November* 1,647
Total Orders received by contractors 2020 December* 1,914
Total Orders received by contractors 2020 4th quarter* 5,517
Total Orders received by contractors 2020* 19,454
Total Orders received by contractors 2021 January* 1,347
Public service and house-building corp. Orders received by contractors 2020 January 206
Public service and house-building corp. Orders received by contractors 2020 February* 193
Public service and house-building corp. Orders received by contractors 2020 March* 235
Public service and house-building corp. Orders received by contractors 2020 1st quarter* 634
Public service and house-building corp. Orders received by contractors 2020 April* 177
Public service and house-building corp. Orders received by contractors 2020 May* 207
Public service and house-building corp. Orders received by contractors 2020 June* 178
Public service and house-building corp. Orders received by contractors 2020 2nd quarter* 562
Public service and house-building corp. Orders received by contractors 2020 July* 176
Public service and house-building corp. Orders received by contractors 2020 August* 88
Public service and house-building corp. Orders received by contractors 2020 September* 185
Public service and house-building corp. Orders received by contractors 2020 3rd quarter* 449
Public service and house-building corp. Orders received by contractors 2020 October* 207
Public service and house-building corp. Orders received by contractors 2020 November* 150
Public service and house-building corp. Orders received by contractors 2020 December* 196
Public service and house-building corp. Orders received by contractors 2020 4th quarter* 554
Public service and house-building corp. Orders received by contractors 2020* 2,198
Public service and house-building corp. Orders received by contractors 2021 January* 187
Companies building for the market Orders received by contractors 2020 January 529
Companies building for the market Orders received by contractors 2020 February* 597
Companies building for the market Orders received by contractors 2020 March* 710
Companies building for the market Orders received by contractors 2020 1st quarter* 1,836
Companies building for the market Orders received by contractors 2020 April* 814
Companies building for the market Orders received by contractors 2020 May* 489
Companies building for the market Orders received by contractors 2020 June* 678
Companies building for the market Orders received by contractors 2020 2nd quarter* 1,981
Companies building for the market Orders received by contractors 2020 July* 1,174
Companies building for the market Orders received by contractors 2020 August* 432
Companies building for the market Orders received by contractors 2020 September* 892
Companies building for the market Orders received by contractors 2020 3rd quarter* 2,498
Companies building for the market Orders received by contractors 2020 October* 997
Companies building for the market Orders received by contractors 2020 November* 699
Companies building for the market Orders received by contractors 2020 December* 1,027
Companies building for the market Orders received by contractors 2020 4th quarter* 2,722
Companies building for the market Orders received by contractors 2020* 9,037
Companies building for the market Orders received by contractors 2021 January* 521
Other private clients Orders received by contractors 2020 January 494
Other private clients Orders received by contractors 2020 February* 668
Other private clients Orders received by contractors 2020 March* 693
Other private clients Orders received by contractors 2020 1st quarter* 1,855
Other private clients Orders received by contractors 2020 April* 790
Other private clients Orders received by contractors 2020 May* 665
Other private clients Orders received by contractors 2020 June* 704
Other private clients Orders received by contractors 2020 2nd quarter* 2,159
Other private clients Orders received by contractors 2020 July* 693
Other private clients Orders received by contractors 2020 August* 627
Other private clients Orders received by contractors 2020 September* 645
Other private clients Orders received by contractors 2020 3rd quarter* 1,965
Other private clients Orders received by contractors 2020 October* 751
Other private clients Orders received by contractors 2020 November* 798
Other private clients Orders received by contractors 2020 December* 691
Other private clients Orders received by contractors 2020 4th quarter* 2,241
Other private clients Orders received by contractors 2020* 8,219
Other private clients Orders received by contractors 2021 January* 639
Source: CBS.
Explanation of symbols

Table description


This table shows the value (expressed in building costs) of the construction of building projects expected shortly. It also shows the value of the actually realised monthly production of building projects. The figures relate to building projects with building costs of 50 thousand euro or more. The total building costs are broken down into alteration and new buildings and in building costs by building phase by type of client. The costs of new buildings are broken down by category of purpose.

Data available from: January 2015.

Status of the figures:
Figures on the latest 12 months are provisional.
Municipalities with non-response are estimated. The later received response of municipalities over previous periods have been processed in the figures of the month in which the building permit was granted. As a result, figures about the same month may vary over time. Twelve months after publication the provisional figures become definite.

Changes as of March 29, 2021:
The figures of January 2021 have been added and the figures of previous 12 months and 4 quarters may have been adjusted.

When will new figures be published?
The new figures will be published approximately 2 months after the reporting month. Figures for the same report month a year earlier then become final.

Description topics

Total building costs
Sum of the building costs for alteration and new building of dwellings
and commercial and industrial building projects.