Civil engineering works; Input price index 2015=100 2012-2024

Civil engineering works; Input price index 2015=100 2012-2024

Deelgebieden Perioden Input price indices (2015=100)
42/43 Civil engineering works 2015 January 100.0
42/43 Civil engineering works 2015 April 100.7
42/43 Civil engineering works 2015 July 101.5
42/43 Civil engineering works 2015 October 98.5
4211a Road construction; brick paving 2015 January 99.4
4211a Road construction; brick paving 2015 April 99.6
4211a Road construction; brick paving 2015 July 100.5
4211a Road construction; brick paving 2015 October 100.3
4211b Road construction; asphalt paving 2015 January 100.8
4211b Road construction; asphalt paving 2015 April 103.7
4211b Road construction; asphalt paving 2015 July 106.4
4211b Road construction; asphalt paving 2015 October 93.1
4212 Railways and underground railway. 2015 January 99.6
4212 Railways and underground railway. 2015 April 100.6
4212 Railways and underground railway. 2015 July 100.2
4212 Railways and underground railway. 2015 October 99.7
4212a Railways; New construction 2015 January 99.6
4212a Railways; New construction 2015 April 100.3
4212a Railways; New construction 2015 July 100.3
4212a Railways; New construction 2015 October 99.9
4212b Railways; Exploitation/Maintenance 2015 January 99.8
4212b Railways; Exploitation/Maintenance 2015 April 100.3
4212b Railways; Exploitation/Maintenance 2015 July 100.2
4212b Railways; Exploitation/Maintenance 2015 October 100.0
4213 Bridges and tunnels; constructio. 2015 January 99.9
4213 Bridges and tunnels; constructio. 2015 April 100.3
4213 Bridges and tunnels; constructio. 2015 July 100.5
4213 Bridges and tunnels; constructio. 2015 October 99.7
4221 Constructions and construction w. 2015 January 100.3
4221 Constructions and construction w. 2015 April 98.9
4221 Constructions and construction w. 2015 July 100.2
4221 Constructions and construction w. 2015 October 100.0
4291 Constructions and construction w. 2015 January 99.6
4291 Constructions and construction w. 2015 April 100.3
4291 Constructions and construction w. 2015 July 101.4
4291 Constructions and construction w. 2015 October 99.3
4312 Site preparation works 2015 January 99.6
4312 Site preparation works 2015 April 100.2
4312 Site preparation works 2015 July 100.8
4312 Site preparation works 2015 October 99.7
4321 Electrical installation works 2015 January 100.1
4321 Electrical installation works 2015 April 101.4
4321 Electrical installation works 2015 July 100.0
4321 Electrical installation works 2015 October 99.0
Source: CBS.
Explanation of symbols

Table explanation


This table shows the input price indices of the costs of labour, materials and equipment for civil engineering works (in Dutch: Grond-, weg- en waterbouw (GWW)). There are ten areas within civil engineering. These areas are based on the standard Classification Products to Activity. For each area a series is calculated based on the price developments of various cost components of which the product to be realised -in this case a civil engineering project- is constructed. The price index for the total of civil engineering is a weighted average of the eight areas. The published price indices of civil engineering are based on the average price level of the month in question. Changes in the overall costs and 'profit and risks' are not taken into account.
Changes compared with twelve months previously are also published for all indices.

Data available from:
The input price indices in this series are available from January 2012 to October 2024.

Status of the figures:
Index figures up to 2023 are definite. Other index figures are provisional.
Since this table has been discontinued, the data is no longer finalized.

Changes as of March 7th 2025:
This table has been discontinued. This table is followed by Price index Civil engineering works, 2020 = 100. See paragraph 3.

Description topics

Input price indices
An index is the ratio between the value of a variable in a given period and the value of that variable in a chosen fixed (reference) period.

In this table the variable is the price trends in civil engineering. This is a weighted average of price movements of the components wages, materials and equipment (tools and machinery).